Location >

Page 2 of 3
Previous | Next


The Onboard Galileo Rubidium and Passive Maser, Status & Performance

  1. The first development activity kicked off at TNT in 1997, and completed in 2000 with one Engineering Model (EM) RAFS1 produced [1].
  2. The updated RAFS1 development started in June 2000 and completed at the beginning of 2002. The industrial consortium is led by TNT with Astrium Germany as the subcontractor for the electronics package. In this phase, the achieved activities include:


    • Improved clock stability with inclusion of thermally regulated base plate. Fig. 1 is the picture of the updated RAFS1.
    • Review of electronics package layout and components in view of flight production.
    • Manufacturing of 5 Engineering Qualification Models (EQM) for lifetime qualification. Fig. 2 shows 5 EQMs without external cover and 5 vacuum chambers for life test with ‘Picotime’ measurement systems.
    • Manufacturing of 1 Qualification Model (QM).
    Besides the vibration and EMC/EMI qualification tests, two radiation tests were carried out at CNES in Toulouse: one test with Galileo orbit simulation, i.e. 4 cycles of 3rad per day during one week, and the other with total dose simulation over the mission duration, i.e. 30 krad continuous radiation @ 400 rad/h during 3 days. No frequency radiation sensitivity was observed during the former test. For the latter test no electronic failure or performance degradation was observed, but it showed the need for wider compensation of the drift of the crystal oscillator. The modification has been implemented on subsequent models. The stability achieved <2.5*10-14/day in ‘best temperature conditions’ under vacuum of the RAFS1 model is shown in Fig. 3.

  3. A third development and qualifications step was initiated at the end of 2001 and completed at the beginning of 2003 with the delivery of an EM, which is the baseline unit for the development of the flight models for GSTB-V2. Two main objectives were achieved [2]:

  4. Figure 1. Picture of the updated RAFS1 once closed including the thermally regulated base plate



    Figure 2. Five EQMs without external cover and vacuum chambers for life test with ‘Picotime’ measurement systems



    Figure 3. RAFS1 EQM frequency data and frequency stability


    • Further optimisation of the physics package to reduce temperature sensitivity resulting better short/mid term stability with a temperature & vacuum environment similar to satellite platform environement ( with +- 1°C temperature changes).
    • Inclusion of a DC/DC converter and the satellite TT&C interface compatible with ESA's new requirements. Fig. 4 shows the performances achieved in term of frequency & time stabilities. Within this configuration RAFS2 shows capabilities to perform time stability close to 1 ns over 1 day.
    Fig. 5 shows the internal construction consisting in RAFS core unit equipped with the thermally regulated baseplate & DC-DC converter.


    Figure 4. RAFS2 core model frequency and time stabilities



    Figure 5. RAFS2 internal construction


  5. In the frame of GSTB-V2, one EQM, one Proto- Flight Model (PFM) and three Flight Model (FM) units have been delivered (integration and tests on satellites are on-going). Two FM spare units are under test and ready to be delivered if required. Table I lists the achieved RAFS performance for GSTB-V2. Fig. 6 shows the measured frequency stability of GSTB-V2 PFM and FM1 to FM4.
  6. Further investigations to improve the flicker floor and temperature sensitivity are under way . Beside the ‘zero’ temperature coefficient provided by the light shift and gaz pressure shift into the cell , the lamp has also been optimized and demonstrates ‘zero’ temperature coefficient. Nevertheless, still temperature coefficients of 5*10-14/°C have been observed. By improving the RF atomic interrogation signal stabilisation circuitry , RAFS has demonstrated stabilities in a range fo 7*10-15 for half of day (Fig. 7) or more observation time. Power shift coefficient has been measured arround 1*10-10/dB change in power. Therefore, few ppm / °C of atomic interrogation signal is required to reach stabilities within the 10-15 range. A carreful worst case analysis of possibles temperature drifts of parameters associated to the automatic gain control has been performed and demonstates the feasibility and possible repeatability of a RAFS having short term stability over one day lower than 1*10-14.
TABLE I. RAFS FOR GSTB-V2 PERFORMANCE ACHIEVED
Parameter Measurement
Frequency stability < 4*10-14 @ 10’000 sec
Flicker floor < 3*10-14 (drift removed)
Thermal sensitivity < 5*10-14 /°C
Magnetic sensitivity < 1*10-13 / Gauss
Mass and volume 3.3 kg and 2.4 liter



Figure 6. GSTB-V2 RAFS2 frequency stability



Figure 7. RAFS3 frequency stability


B. Development & Qualification Activities of Passive Hydrogen Maser
The space hydrogen maser will be the master clock on the Galileo navigation payload. The first maser development activity tailored to navigation applications was kicked off in 1998. It was initiated by the development of an active maser at ON However, at the Galileo definition phase, it became clear that the accommodation of the active maser on the satellite was too penalizing in term of mass and volume, and the excellent frequency stability performances of the active maser were not required. In 2000 it was re-orientated towards the development of a PHM based on the industrial design and ON heritage on active maser studies.

The development of the EM (Fig. 8) [3] was completed at the beginning of 2003, under the lead of ON with Galileo Avionica (GA) subcontractor for the electronics package and TNT supporting the activity in view of the future PHM industrialisation. The instrument has been under continuous test since June 2003 for assessment of long term performance and early identification of reliability and lifetime problems. This EM model (Fig. 9) shows the frequency and time stability at first stage. By comparison, about 5 years of design optimisation and intensive testing has been necessary to reach such level of performances with the RAFS.

The industrialization activity aimed at PHM design consolidation for future flight production was started in January 2003 [4]. The industrial consortium is led by GA designing the electronics package with TNT responsible for the manufacturing of the physical package and the ON supporting the transfer of technology. The overall structure of the instrument was reviewed to increase compactness and to ease the Assembly, Integration and Test (AIT) processes on the satellite by the inclusion of an external vacuum envelope. Main efforts in the industrialization frame focused on the definition of repeatable and reliable manufacturing processes and fixtures, particularly for the physical package:


Figure 8. Picture of PHM EM. ON&GA



Page 2 of 3
Previous | Next